As promised...Observations about La Terrasse

The work on the exterior of the building seems complete but the scaffolding on the street side remains in place. Some of the units are occupied by full time unit owners and some employees. The other units have patio/balcony door and slider frames waiting to be installed. The lobby is filled with furniture and is not operating. I suspect that most timeshare units do not have furniture. Stored in the garage below the building is a lot of building materials and boxed interior elements. The pool area looks intact but has not been cleaned and the pool is not filled. However, the terrace garden is in good shape and open. Staff thinks that the timeshare units might reopen sometime in January but did not speculate of when in January.

Last edited by smalbany; 12/16/2018 12:44 PM.