Traveltalkonline.com Forums

.


SXM Cruise Schedule TTOL Sponsors SXM Travel Calendar
Forum Statistics
Forums39
Topics40,583
Posts329,227
Members26,912
Most Online4,031
Dec 15th, 2024
Top Posters(30 Days)
BEERMAN 25
Manpot 22
GaKaye 15
Kennys 13
Jerry_R 12
Member Spotlight
Southshore
Southshore
Mississauga, ON, Canada
Posts: 889
Joined: January 2004
Today's Birthdays
jt716
Who's Online Now
4 members (sxmpete, 3 invisible), 318 guests, and 76 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Joined: Nov 2004
Posts: 91
R
Traveler
OP Offline
Traveler
R
Joined: Nov 2004
Posts: 91
The walls are going up at Cocoa Beach; earlier this week, some interior block work, but most of this week, the guys are working on concrete forms to pour the outer wall. cf. pics attached

There's work going on at the carbet site, but it's a bigger site and there is nothing different to pick up with a picture. Most of this week, they seem to be leveling the site and using a compacter to bang down the soil that they had shifted to put in the underpinnings.


OOPS. sorry about the one pic orientation!

Attached Images
IMG_6079.JPG IMG_6080.JPG IMG_6081.JPG IMG_6082.JPG IMG_6083.JPG
Last edited by RunnernReader; 03/08/2019 11:48 AM.
SXM Sponsors
.
Joined: Aug 2000
Posts: 84,971
Likes: 55
Traveler
Offline
Traveler
Joined: Aug 2000
Posts: 84,971
Likes: 55
Thanks for the update. That one picture sure illustrates better how the structure is built back almost into that hill. I guess that will provide some protection from winds from behind.


Carol Hill