Traveltalkonline.com Forums

.


SXM Cruise Schedule TTOL Sponsors SXM Travel Calendar
Forum Statistics
Forums39
Topics40,582
Posts329,208
Members26,911
Most Online4,031
Dec 15th, 2024
Top Posters(30 Days)
BEERMAN 22
Manpot 18
GaKaye 16
Jerry_R 13
Kennys 13
Member Spotlight
BeachKitten
BeachKitten
Maryland/DC Metro
Posts: 3,279
Joined: November 2009
Today's Birthdays
jules67
Who's Online Now
6 members (patentshark, boucharda, Jerry_R, SXMScubaman, CaroleS, 1 invisible), 314 guests, and 57 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Joined: Nov 2004
Posts: 91
R
Traveler
OP Offline
Traveler
R
Joined: Nov 2004
Posts: 91
The walls are going up at Cocoa Beach; earlier this week, some interior block work, but most of this week, the guys are working on concrete forms to pour the outer wall. cf. pics attached

There's work going on at the carbet site, but it's a bigger site and there is nothing different to pick up with a picture. Most of this week, they seem to be leveling the site and using a compacter to bang down the soil that they had shifted to put in the underpinnings.


OOPS. sorry about the one pic orientation!

Attached Images
IMG_6079.JPG IMG_6080.JPG IMG_6081.JPG IMG_6082.JPG IMG_6083.JPG
Last edited by RunnernReader; 03/08/2019 11:48 AM.
SXM Sponsors
.
Joined: Aug 2000
Posts: 84,969
Likes: 55
Traveler
Offline
Traveler
Joined: Aug 2000
Posts: 84,969
Likes: 55
Thanks for the update. That one picture sure illustrates better how the structure is built back almost into that hill. I guess that will provide some protection from winds from behind.